25 Contract work in progress

 
 31-Dec-200931-Dec-08Change
Contract work in progress19,90421,704-1,800
Total19,90421,704-1,800

As at 31 December 2009, contract work in progress recorded a balance of Euro 19,904 thousand and concerned work on plants as well as the development of commissions lasting several years for third parties.